At long last, what feels like a major milestone has been achieved – the building warrant pack is complete and has been submitted to the Highland Council for review and approval!
This has been so much more of an effort than we ever imagined.
Every SIP panel, roof tile, larch board, power outlet, plug socket, door material, light switch and window frame has had to be specified, documented and checked.
We’ve had the SAP assessment completed by the Energy Consultant and we’re very pleased with the energy rating for the house. It should be snug and cheap to heat, with an Air Source Heat Pump, underfloor heating and tons of insulation.
We’ve had our challenges with the access road. The gradient of the croft leading up to the building plot is pretty steep, and the engineer has had to wind the road around the plot much more than we’d originally thought to keep the gradient of the road useable and within building regs. That means more road, more excavation and more expense, but it has to be done.
Now we sit back and wait, hoping for a smooth approvals process so that we can finally start looking at the build itself next Spring.
We are creeping forwards! Slowly and painfully, but progress is being made…

Fingers crossed for you.
LikeLiked by 1 person
Thank you Linda! 🙏
LikeLike
No wonder it was arduous, you needed a SAP assessment! Exciting times x
LikeLiked by 1 person
Lol. There’s no getting away from SAP, is there…..😬😊
LikeLike
standard assessment procedure (SAP) to determine the energy and environmental performance of dwellings. Not an ERP system in sight👍
LikeLike
Building in Scotland sounds like no easy feat!
LikeLiked by 1 person
It’s a lengthy process! 🙄
LikeLiked by 1 person
Yikes. Good luck. Any updates?
LikeLiked by 1 person
Building warrant granted! Yay. Now we wait to get building and groundwork schedules in place for the Spring 👍